2009 Safety Path Construction

______________________________________________________

2009 Safety Path Program
Segment No. Segment Description Est. Segment Length (LF) Segment Est. Cost
No. 7 & 8 Inkster Road (westside, south of Maple to Fairview Colony Club) 3253 $394,500
No. 11 14 Mile Road (northside, between Farmington Road and Orchard Lake) 2, 060 $247,801
No. 15 Haggerty Road (eastside, south of Maple Road) 1,498 $185,474
No. 18 Maple Road (northside, east of Halstead Road) 290 $50,750
No. 21 Maple Road (southside, west of Farmington Road) 170 $32,196
No. 24 Maple Road (southside, west of Orchard Lake Road) 216 $42,950
No. 38 Oakley Park Road (southside, west of Twin Beach Elementary) 1,580 $188,290
No. 42 Willow Road (southside, east of Keith Road) 688 $124,536
No. 43 Willow Road (northside, east of Weathervane) 331 $52,454
No. 45 Lochaven Road (westside, south of Hunt) 2,115 $284,701
No. 47 Commerce Road (northside, east of Hiller) 2,746 $377,014
No. 48 Willow Road (southside, Lochaven east to Green Bay) 1,586 $230,555
No. 49 Willow Road (southside, west of Hiller Road) 1,229 $206,020
No. 62 Haggerty Road (eastside, north of Pontiac Trail) 810 $124,876
TOTALS 18,637 $2,545,580

Written public comments will be received through January 16, 2009.  During the review period, the township design consultants will be available on Wednesdays and Fridays from 9 am to 12 pm to field questions regarding the project.   Submit written comments via e-mail, fax (248-451-4871) or mail.  